Leander ISd

Shot blast to remove asphaltic adhesive

Faubion Elementary School

Prep for moisture mitigation system

We were contracted to shot blast to remove existing asphaltic adhesive (tested negative for asbestos). After shot blasting to create a CSP of 3, flooring contractor applied an epoxy moisture mitigation system due to high levels of moisture in the concrete. After installing the epoxy, vct flooring was installed.

  1. Shot blast 4,992 square feet to Concrete Surface Profile (CSP) of 3
  2. Edge grind perimeter to a CSP of 1-2
  3. Supplied all necessary power to complete project
  4. Project Duration: 1 day including all mobilization (192 miles round trip)

Return to our Portfolio Page

Top